DTIC Submission Windows and Deadlines: When to Apply for Each Programme
Updated: 1 day ago
The most expensive mistake on a dtic incentive is applying too late. Costs you incur before the right moment usually do not qualify, and missing a claim deadline can cancel an approved grant. Here is when to apply for each programme, and the deadlines that follow.

Manufacturing Support Programme (MSP)
Applications are accepted during designated application windows. The dtic does not always publish the dates, so check before you plan your spending.
Apply before you buy or start using the assets. Equipment already in use does not qualify.
If the dtic has not responded 30 days after a complete application, you may proceed at your own risk.
Commercial production must start within 180 days of approval, and the first claim is due within six months of production starting.
Black Industrialists Scheme (BIS)
Applications are open on a rolling basis, but since 1 June 2026 only through the dtic's online portal (OIS).
Apply before the project starts. If there is no response 60 days after a complete application, you may proceed at your own risk.
Financial close must be reached within 90 days of approval, and the first claim is due within six months.
Automotive Investment Scheme (AIS)
Timing is tied to your start of production. Component and tooling makers apply 90 to 120 days before it, and vehicle manufacturers 120 to 180 days before.
Claims are due within four months of the end of each claim period.
Critical Infrastructure Programme (CIP)
Open on a rolling basis. Submit a complete application before construction starts.
Work may begin after the dtic's site visit, at your own risk. The dtic has indicated a decision in around 60 working days once the application is complete.
Agro-Processing Support Scheme (APSS)
Applications are accepted during designated windows, and only through the OIS portal since 1 June 2026.
The project must start within 90 days of approval, and the first claim is due within six months.
Export Marketing and Investment Assistance (EMIA)
Apply three to six months before the trade show or mission.
Claim within two months after the event, and submit a feedback report six months later, or you are excluded from EMIA for six months.
Up to four successful individual applications a year are allowed, plus two more for events in Africa. No physical events are supported between 15 December and 5 January.
Interesting Facts About Timing
The "proceed at your own risk" rule means silence from the dtic is not a rejection. After 30 days (MSP and APSS) or 60 days (BIS) you can start, but approval is still not guaranteed.
In June 2026 the dtic told Parliament that demand for incentives exceeds the available budget, so applying early in a window matters.
Approval does not end your deadlines. Most programmes cancel a grant if the first claim is not submitted within six months.
A Simple Rule of Thumb
Start the application at least three months before you plan to sign purchase orders, start construction or book a trade show. That leaves time for the business plan, the dtic's questions and any changes to your project.
Planning a project? Contact Hilder Consulting and we will map out the deadlines for your programme.
Based on current dtic programme guidelines, the dtic notices of 1 June 2026 and the dtic briefing to Parliament on 17 June 2026. Approval is at the dtic's discretion and subject to available funds.